Latest update on road - due to weak soil conditions behind the ICTC building, part of the road will not be constructed.
Showing posts with label IM. Show all posts
Showing posts with label IM. Show all posts
The project include widening of the road near to the water tank which then link to the back of new ICTC building, pass the PAPHRSB Institute of Health Science and straight on to the entrance road to the neighbouring Institute Teknologi Brunei. Construction work in progress.
Project: Proposed Pengiran Anak Puteri Rashidah Sa'adatul Bolkiah Institute of Health Sciences (PAPRSB IHS) Building Extension, Universiti Brunei Darussalam
Location: Between the new Information Technology Communications Centre and Pengiran Anak Puteri Rashidah Sa'adatul Bolkiah Institute of Health Sciences current building.
Class: 6 Category: 2 Construction period: 20 months
Tender fee: B$5,000 (non-refundable)
Tender open: 13th October 2010
Tender close: 2.00pm, 16th November 2010
Tender collection: The Bursar Office, Administration Building, Universiti Brunei Darussalam
Last date of collection: 2nd November 2010
Location: Between the new Information Technology Communications Centre and Pengiran Anak Puteri Rashidah Sa'adatul Bolkiah Institute of Health Sciences current building.
Class: 6 Category: 2 Construction period: 20 months
Tender fee: B$5,000 (non-refundable)
Tender open: 13th October 2010
Tender close: 2.00pm, 16th November 2010
Tender collection: The Bursar Office, Administration Building, Universiti Brunei Darussalam
Last date of collection: 2nd November 2010
We had our first MBWA (management by walking about) last week and visited the New Residential College, Male and Female Residential College, Visiting Lecturer Quaters, Universiti Mosque, Institute of Medicine, Faculty of Science and Student Affairs Building.
And along the way we met some students and also a few wild animals :)
And along the way we met some students and also a few wild animals :)
The inspection was held on the 8th December 2009 and concentrated mainly on the defects liability period for building and mechanical and electrical (M&E) works.
Today we received the second container of furniture for the IM building. Two more containers will arrive tomorrow. I was informed that everyone from the supplier's company will be working extra hours in the next few days installing and fixing the furniture. Very efficient! The dateline for moving into the new building is less than 2 weeks away.